|
|
Estimate Cost and Schedule Empirically
|
||||||||
|
"A good cost estimator should never make an estimate that deviates from the actual cost at delivery by more than 20 percent. A good schedule estimate should be within 5 percent of actual schedule at least 95 percent of the time, and should not deviate by more than 12 percent less than the actual schedule." --Capers Jones Estimate Cost and Schedule Empirically Software development projects historically have a poor record when it comes to project estimation. Statistics repeatedly show that the chance of a project completing on-time and under-budget is less than one in ten. Further, the chances are worse if the project is a large-scale, complex, software-intensive project, the kind the 16 Critical Software Practices were designed to help. This estimation difficulty is not a reflection of our inability to forecast and analyze a new job. Rather, it is a reflection of the inherent complexity of software development projects, the multitude of ever-present factors that can influence cost and schedule, and the inadequacy of our estimation models to forecast the resources a project will take. There are a number of ways to estimate the cost and schedule
for a software project. One of the most effective methods is
organizational experience-i.e., what the cost and schedule results
have been for similar efforts. The reason this estimation basis
can be so powerful is that it aggregates the multitude of factors
present in a given organization The cost and schedule estimation approach must be designed to take advantage of the information available about prior efforts to estimate future ones. |